Project Server 2013 and manually entered baselines not saving to database

**Quick publish article.  Further tests follow**
**Update:  Only appears to apply to on-premise installs.  Project Online is unaffected**

Issue:  When manually editing Baseline(0-10) timephased data via task usage in MS Project Client, data is not saved to database.

Tested on:  SEPT 2015 PU (Server and Client)

Prep:
-------------------------------------------------------
Create a project with one task on it.  
add a resource from pool and assign to the task at 100%
Set Baseline (0)
Publish plan

Test:  Query DB and see timephased data populated correctly



Issue 1 Repro
-------------------------------------------------------
Edit Baseline Work values in Task Usage view
Save and Publish

Test:  Query DB and see timephased data is not changed



Issue 2 Repro
-------------------------------------------------------
Add Baseline 10 to task usage view
Manually enter values into timephased cells for Baseline10
Save and Publish

Test:  Query DB and see timephased data is not changed




Issue 3 Repro
-------------------------------------------------------
Close MSP file
Remove from Cache
open file

Test:  See that previously edited values in Baseline 0 and Baseline 10 are missing.  Original Baseline data (set using Set Baseline) is displayed


Summary findings
-------------------------------------------------------
It looks like manually edited baseline values are not moving from Cache to Database on Save and therefore the reporting db isnt being updated.




SQL Script for test:
-------------------------------------------------------

--Baseline 0
SELECT         b.TimeByDay, b.AssignmentBaselineWork
FROM (SELECT * FROM MSP_EpmProject WHERE ProjectName = 't1bltest') P
INNER JOIN MSP_EpmAssignment A 
         on           p.projectuid = a.projectuid
INNER JOIN MSP_EpmAssignmentBaselineByDay B 
         on           a.AssignmentUID = b.AssignmentUID
WHERE          b.BaselineNumber = 0

--Baseline 10:
SELECT         b.TimeByDay, b.AssignmentBaselineWork
FROM (SELECT * FROM MSP_EpmProject WHERE ProjectName = 't1bltest') P
INNER JOIN MSP_EpmAssignment A 
         on           p.projectuid = a.projectuid
INNER JOIN MSP_EpmAssignmentBaselineByDay B 
         on           a.AssignmentUID = b.AssignmentUID
WHERE          b.BaselineNumber = 10

Comments

  1. I think this is an issue I've run into before. You need to change the scalar value, i.e. the total work or some field for the baseline in question. That's what triggers MPP to see that the baseline has changed and will then cause it to save the timephased values. See if that works.... (http://azlav.umtblog.com/2012/01/10/capturing-custom-timescaled-data-in-project-professional-part-i/)

    ReplyDelete

Post a Comment

Popular posts from this blog

TPG Apps Highlights - Risk Matrix #projectonline #projectserver #risk

This post is the first of a series to highlight the apps available for Project Server and Project Online from the SharePoint store  ( https://store.office.com/search.aspx?productgroup=SharePoint&qu=tpg ) and direct via your local TPG office. The first of this series will look at the s imple plug-and-play apps that all users of Project Online can make use of quickly and easily.   T hese are: Risk Matrix  Milestone Trend Analysis (MTA) WBS Chart viewer Next we will focus on the challenge of  Resource Request Supply and Demand by demonstrating our more recent TeamLink and TeamManager apps. Team Manager App is a Resource Manager/Owner app for allocating resource supply to Projects and BAU activities and monitoring demands against commitments Team Link App is a PM tool for monitoring Project demands vs the supply provided by the Resource Managers  Finally I will highlight some of the benefits of our integration tools when used in the context of Project Online

Restoring PWA Site to another Web App in the same Farm

The scenario is this: SharePoint 2016 Farm with Project Server Two Web Apps Development UAT One PWA on Development Web App. I want to copy the PWA Site on Development web app to UAT to support a testing cycle. As far as I knew there were two options: 1) Content Database Restore and Attach Process would be backup your Dev Content Database, Restore to a new Content Database for QA, then mount the database on the appropriate web app and your off.... Problem:  Although you can do this with the -AssignNewDatabaseID switch in Powershell (to avoid two content db's having the same database id) the Site Collection (PWA) in the db still retains its SiteID which means there is a duplicate SiteID in the Configuration Database.  This stops the PWA site being created and alllocated correctly and becomes essentially orphaned. This method is only any good for MOVING not COPYING Back to the drawing board... 2) Backup-SPSite / Restore-SPSite I didn't believe this w

Migration Project Server (2010 to 2019) Issue 1 - Upgrading from 2013 to 2016 - Error encountered while migrating project data in Content database. The instance of the SQL Server Database Engine cannot obtain a LOCK resource at this time. Rerun your statement when there are fewer active users

I was intending to write a set of posts on the topic of migrating SharePoint and Project Server from 2010 on premise through 2013, 2016 to 2019 Azure, using SQL Managed Instance as the backend SQL Service.  This set of posts are still getting drafted and updated as we move through this cycle, but I came across a huge blocker this week that I wanted to post on, whilst it was fresh. Our Azure migration machines (2013 and 2016) are: - dual core 2.3ghz - 28GB Ram 2013 server is Windows Server 2012 R2 running SQL 2012 SP1 2016 server is Windows Server 2016 running SQL 2014 SP1 The Project Server dataset we are dealing with here is c.100GB (50% archive data). The uplift from SP/PS 2010 to 2013 went without a hitch over a 2.5hr period which was a huge win.  However when attempting to upgrade to 2016 we hit a hitch. Firstly some background:  When you perform the Migrate-SPProjectDatabase command, the following will happen (well it certainly did to us) - the ProjectWebApp DB fro