Using the RESUME field to reschedule incomplete work #projectserver

Since MS provided the ability to plan only using PWA, this has been a really useful feature for some users.  However there has always been a (certainly from my perspective) perceived issue, in that the ability to reschedule incomplete work into the future (a key component of the planning cycle) was only available in MS Project client.

The other day I was asked by a customer how they could get around this issue.  They use PWA extensively (cost reasons) for planning but were struggling with realising correct resource forecast data as they PM's were not able to re-forecast their remaining work schedule.

As we had recently patched the Project Server to 2013 SP1 + 0614CU I thought I would look at the STOP/RESUME fields in the Project views to see if these were editable, and surprise surprise they were.

The stop/resume fields are how MS Project handles task splits and the "update remaining work to restart after" component of rescheduling.  The Stop field will indicate the last day that progress was added to the task (either via % Complete or Timephased Actual Work edits/status updates) and by default the resume field will be the next day (or minute, in truth)

If you edit the resume field to a date in the future, then the task becomes split and the remaining work moves forward to restart from that date.

Don't ask me to explain multiple or manual splits.  I can't

Anyhoo... the repro

Firstly create a new project, with one task on it with 10d duration for simplicity of querying, and assign one resource to the assignment and publish the schedule


As the user assigned to the task, complete the first day of actual work and submit

As the Project Owner, approve the task.  Then go into Approval History and publish the assignment

Wait until it publishes

Then open the project in PWA for editing.

Set the Resume date to some time in the future, in this example 18th August
Note the finish date changes

Now query the assignmentbyday table and see the work move forward (ignore the nulls in my results, these have been replaced in my query to make it easier to discern between 0's and 8's!)


Notice that the planned work now has a gap between the 1d actuals assigned and the Resume date of 18 August

HURRAH!!!




Comments

Popular posts from this blog

TPG Apps Highlights - Risk Matrix #projectonline #projectserver #risk

This post is the first of a series to highlight the apps available for Project Server and Project Online from the SharePoint store  ( https://store.office.com/search.aspx?productgroup=SharePoint&qu=tpg ) and direct via your local TPG office. The first of this series will look at the s imple plug-and-play apps that all users of Project Online can make use of quickly and easily.   T hese are: Risk Matrix  Milestone Trend Analysis (MTA) WBS Chart viewer Next we will focus on the challenge of  Resource Request Supply and Demand by demonstrating our more recent TeamLink and TeamManager apps. Team Manager App is a Resource Manager/Owner app for allocating resource supply to Projects and BAU activities and monitoring demands against commitments Team Link App is a PM tool for monitoring Project demands vs the supply provided by the Resource Managers  Finally I will highlight some of the benefits of our integration tools when used in the context of Project Online

Restoring PWA Site to another Web App in the same Farm

The scenario is this: SharePoint 2016 Farm with Project Server Two Web Apps Development UAT One PWA on Development Web App. I want to copy the PWA Site on Development web app to UAT to support a testing cycle. As far as I knew there were two options: 1) Content Database Restore and Attach Process would be backup your Dev Content Database, Restore to a new Content Database for QA, then mount the database on the appropriate web app and your off.... Problem:  Although you can do this with the -AssignNewDatabaseID switch in Powershell (to avoid two content db's having the same database id) the Site Collection (PWA) in the db still retains its SiteID which means there is a duplicate SiteID in the Configuration Database.  This stops the PWA site being created and alllocated correctly and becomes essentially orphaned. This method is only any good for MOVING not COPYING Back to the drawing board... 2) Backup-SPSite / Restore-SPSite I didn't believe this w

Migration Project Server (2010 to 2019) Issue 1 - Upgrading from 2013 to 2016 - Error encountered while migrating project data in Content database. The instance of the SQL Server Database Engine cannot obtain a LOCK resource at this time. Rerun your statement when there are fewer active users

I was intending to write a set of posts on the topic of migrating SharePoint and Project Server from 2010 on premise through 2013, 2016 to 2019 Azure, using SQL Managed Instance as the backend SQL Service.  This set of posts are still getting drafted and updated as we move through this cycle, but I came across a huge blocker this week that I wanted to post on, whilst it was fresh. Our Azure migration machines (2013 and 2016) are: - dual core 2.3ghz - 28GB Ram 2013 server is Windows Server 2012 R2 running SQL 2012 SP1 2016 server is Windows Server 2016 running SQL 2014 SP1 The Project Server dataset we are dealing with here is c.100GB (50% archive data). The uplift from SP/PS 2010 to 2013 went without a hitch over a 2.5hr period which was a huge win.  However when attempting to upgrade to 2016 we hit a hitch. Firstly some background:  When you perform the Migrate-SPProjectDatabase command, the following will happen (well it certainly did to us) - the ProjectWebApp DB fro